In St. Paul, the two agencies that review stormwater treat permeable paving differently. The Capitol Region Watershed District's rules list permeable pavement as an infiltration area, but the City's January 2026 Stormwater Management Design Standards treat pervious pavement as impervious surface and do not accept it as a BMP for infiltration, volume control or water quality. Projects in the district need both the district permit and City site plan approval, so the City's position still matters there.
That split is the honest starting point for any St. Paul project. Permeable resin-bound may be worth proposing on some district-permitted sites if both reviewers accept it, works as a design amenity on others, and is never a stormwater measure when it is simply laid over an old slab.
City standards, watershed district rules and which applies to you
Two watershed districts cover most of the city and have run joint stormwater rules since 2006. Where the Capitol Region or Ramsey-Washington Metro Watershed District requires a permit, the applicant must get the district permit before any City permit is issued. In the Mississippi WMO and Lower Mississippi River WMO areas, the City does the permitting itself under its Design Standards.
The City's thresholds: land disturbance over a quarter acre (10,890 square feet) that triggers site plan review needs a Stormwater Management Plan, rate control and erosion control; construction activity of an acre or more adds volume reduction of 1.1 inches over new and fully reconstructed impervious surfaces, plus water quality. Capitol Region, amended effective September 13, 2023, also requires 1.1 inches over new and reconstructed impervious surfaces on projects disturbing one acre or more, and on some smaller sites next to wetlands, streams or public waters, and it is under those rules that a permeable section can be considered for credit.
Bluffs, karst and the river: what limits infiltration here
St. Paul's Design Standards prohibit infiltration in a long list of places that are common in this city: within 1,000 feet up-gradient or 100 feet down-gradient of active karst features, with less than 3 feet of separation to seasonally saturated soil or bedrock, in predominantly clay soils, where contamination could be mobilized, and anywhere infiltration could undermine bluff lines, steep slopes or levees. The standards also map No Infiltration Zones.
Along the Mississippi bluffs and near the levees, a permeable resin-bound surface would need a lined, underdrained base and would serve mainly as a durable, quick-draining finish. Long winters, deep frost and de-icing salt shape the rest of the brief: the engineer should size the open-graded base for frost and plan winter care that keeps sand out of the voids.
Where permeable resin-bound still makes sense in St. Paul
- Capitol Region projects, such as redevelopment along the University Avenue corridor or near Como Lake, where the district's rules list permeable pavement as an infiltration area. Ask both the district and the City early whether a resin-bound section can count toward the 1.1 inches.
- College and hospital campus plazas wanting accessible, quick-draining walks alongside the stormwater practices that carry the credit.
- Residential patios and garden paths below permit thresholds, where owners simply want water to soak in on suitable soil.
- Bluff-top terraces as a lined, underdrained finish where infiltration is off the table.
Owners who only want to refresh a sound slab, with no stormwater goal, should look at our St. Paul concrete resurfacing page instead.
Review steps, and how Resin Rock supports the project
Start with the watershed: confirm with Capitol Region or Ramsey-Washington Metro whether a district permit is needed, and ask early how the district wants a permeable section modeled. Then the City's site plan review, run with Public Works and Safety and Inspections, checks the plan against the Design Standards before a building permit is released.
Resin Rock ships binder, stone blends, trims and Rock Crete permeable sub-base to St. Paul and provides the documentation engineers need. We connect owners with approved installers and train new crews through our Minnesota installer training.
Before you specify permeable resin-bound in St. Paul
- Identify the watershed district or WMO for the parcel before design starts
- Check the site against the City's No Infiltration Zones and karst setbacks
- Measure disturbance against the quarter-acre and one-acre thresholds
- Confirm 3 feet of separation to saturated soil or bedrock
- Agree with the reviewer how the permeable area is counted in impervious totals
Common questions about permeable resin-bound in St. Paul
Will the City of St. Paul credit permeable resin-bound toward my volume requirement?
Not under its own Design Standards. The January 2026 edition counts pervious pavers and pavement as impervious surface and says they are not an acceptable BMP for infiltration, volume control or water quality. Capitol Region's rules do list permeable pavement as an infiltration area, but district projects still need City site plan approval, so ask both reviewers how a resin-bound section would be counted before you rely on it.
Can a permeable surface lower my Storm Sewer System Charge?
Possibly, for larger parcels. The charge is set by land-use class and parcel size, with a flat charge for small homes, condos and townhouses. Under the City's January 2026 review policy, Public Works can adjust other parcels' charges when a request filed within 30 days of the annual bill shows a lower peak runoff rate. Homes under a third of an acre, condos and townhouses get no adjustment, and the policy does not mention permeable paving.
If we only resurface our parking lot with resin-bound, do we need a stormwater plan?
The City's thresholds are tied to land disturbance and site plan review, so a surface treatment that doesn't disturb soil may not trigger one, but confirm with Public Works before you start. Either way, an overlay on existing asphalt is not a stormwater practice: water passes through the finish and then runs off the old pavement.
Our lot is near the river bluff. Is infiltration allowed?
Often not. The Design Standards prohibit infiltration where it could affect bluff lines, steep slopes or levees, and restrict it on sites adjacent or upgradient to them. A permeable resin-bound surface can still be built over a lined, underdrained base as a durable finish, but your engineer should not count on it for infiltration there.
Official sources for St. Paul
- St. Paul Public Works: Site Plan Review (stormwater requirements)
- St. Paul Stormwater Management Design Standards, January 2026 (PDF)
- Capitol Region Watershed District: Watershed Rules
- St. Paul: Storm Sewer System Charge
Local rules change. We last checked these sources in October 2026. Confirm current requirements with the reviewing agency before you design, and treat this page as a starting point, not engineering or permitting advice.